Project Milestones and Schedule

MIT_002
(MIT, Yu-Chih Ko)

 

The EITA-B&M 2017 project was started in July 2016 and runs through Spring 2017.
 
Date
Project Milestone Description
Status 
July 19, 2016
Propose the conference and the  location of the EITA-B&M 2017.
Done
July 21, 2016
Propose the theme of the EITA-B&M 2017.
Done
July 23, 2016
Set up the website of the EITA-B&Ms 2017. 
Done
July 26, 2016
Decide the conference date.
Done
August 1, 2016
Checkpoint 1: project reviews and progress monitoring. 
Done
August 1, 2016
Start to draft the description of the conference theme.
Done
August 8, 2016
Start to propose the workshop schedule and the topics.
Done
August 15, 2016
Start to form the organizing committee and the program committee.
Done
August 20, 2016
Recommend the conference chair of the EITA-B&M 2017. Done
August 26, 2016
Confirm the conference chair of the EITA-B&M 2017.
Done
August 27, 2016
Recommend the Project Manager of the EITA-B&M 2017. 
Done
August 31, 2016
The website of the EITA-B&M 2017 is ready to support the event.
Done
September 1, 2016
Checkpoint 2: project reviews and progress monitoring. Done
September 15, 2016
Confirm the Project Manager of the EITA-B&M 2017.
Done
September 30, 2016
Finalize the website of the EITA-B&M 2017.
Done
October 1, 2016
Checkpoint 4: project reviews and progress monitoring.
Done
October 1, 2016
Start to invite speakers. 
Done
October 19, 2016
The first local organizing committee meeting.
Done 
November 1, 2016
Checkpoint 5: project reviews and progress monitoring. Done 
November 1, 2016  The first draft registration form ready.  Done 
November 15, 2016 Finalize the conference themes and the program schedule. Done 
December 1, 2016
Checkpoint 6: project reviews and progress monitoring.
Done 
December 4, 2016  The first draft conference invitation letter ready.  Done 
December 7, 2016  The first draft conference invitation letter ready.   Done 
December 10, 2017 The first draft template of the conference program ready.  Done 
December 10, 2017  The first draft template of the conference proceedings ready.  Done 
December 15, 2016  Start to draft the conference program and the proceedings  Done 
December 22, 2016  The first draft of the conference program (without photos) ready.  Done 
December 29, 2016  The official conference themes and the organizing committee ready.  Done 
January 1, 2017
Checkpoint 7: project reviews and progress monitoring.
Done 
January 5, 2017  The first draft conference program ready (with photos).  Done 
January 15, 2017  The first draft invited guest list ready.  Done 
February 1, 2017
Checkpoint 8: project reviews and progress monitoring.
Done 
February 1, 2017  The first draft conference proceedings ready. Done 
February 5, 2017  The first draft conference program (with the photos version) ready.  Done 
March 1, 2017
Checkpoint 9: project reviews and progress monitoring. Done
March 1, 2017  The official conference program ready (without photos).  Done
March 15, 2017  The first draft confirmed conference attendee list ready. Done
March 15, 2017
The official conference program ready (with photos).
Done
April 1, 2017
Checkpoint 10: project reviews and progress monitoring. Done
April 1, 2017  The confirmed conference attendee list ready.  Done 
April 15, 2017
The official conference proceedings ready. 
Done
April 27, 2017
Local Management Meeting.
Done
April 28, 2017
The EITA-B&M 2017 starts.
Done
April 28, 2017
The EITA-B&M 2017 ends.
Done
April 30, 2017
The final conference programs and proceedings ready.
Done

 