Project Milestones and Schedule
The EITA-B&M 2017 project was started in July 2016 and runs through Spring 2017.
Date |
Project Milestone Description |
Status |
---|---|---|
July 19, 2016 |
Propose the conference and the location of the EITA-B&M 2017. |
Done |
July 21, 2016 |
Propose the theme of the EITA-B&M 2017. |
Done |
July 23, 2016 |
Set up the website of the EITA-B&Ms 2017. |
Done |
July 26, 2016 |
Decide the conference date. |
Done |
August 1, 2016 |
Checkpoint 1: project reviews and progress monitoring. |
Done |
August 1, 2016 |
Start to draft the description of the conference theme. |
Done |
August 8, 2016 |
Start to propose the workshop schedule and the topics. |
Done |
August 15, 2016 |
Start to form the organizing committee and the program committee. |
Done |
August 20, 2016 |
Recommend the conference chair of the EITA-B&M 2017. | Done |
August 26, 2016 |
Confirm the conference chair of the EITA-B&M 2017. |
Done |
August 27, 2016 |
Recommend the Project Manager of the EITA-B&M 2017. |
Done |
August 31, 2016 |
The website of the EITA-B&M 2017 is ready to support the event. |
Done |
September 1, 2016 |
Checkpoint 2: project reviews and progress monitoring. | Done |
September 15, 2016 |
Confirm the Project Manager of the EITA-B&M 2017. |
Done |
September 30, 2016 |
Finalize the website of the EITA-B&M 2017. |
Done |
October 1, 2016 |
Checkpoint 4: project reviews and progress monitoring. |
Done |
October 1, 2016 |
Start to invite speakers. |
Done |
October 19, 2016 |
The first local organizing committee meeting. |
Done |
November 1, 2016 |
Checkpoint 5: project reviews and progress monitoring. | Done |
November 1, 2016 | The first draft registration form ready. | Done |
November 15, 2016 | Finalize the conference themes and the program schedule. | Done |
December 1, 2016 |
Checkpoint 6: project reviews and progress monitoring. |
Done |
December 4, 2016 | The first draft conference invitation letter ready. | Done |
December 7, 2016 | The first draft conference invitation letter ready. | Done |
December 10, 2017 | The first draft template of the conference program ready. | Done |
December 10, 2017 | The first draft template of the conference proceedings ready. | Done |
December 15, 2016 | Start to draft the conference program and the proceedings | Done |
December 22, 2016 | The first draft of the conference program (without photos) ready. | Done |
December 29, 2016 | The official conference themes and the organizing committee ready. | Done |
January 1, 2017 |
Checkpoint 7: project reviews and progress monitoring. |
Done |
January 5, 2017 | The first draft conference program ready (with photos). | Done |
January 15, 2017 | The first draft invited guest list ready. | Done |
February 1, 2017 |
Checkpoint 8: project reviews and progress monitoring. |
Done |
February 1, 2017 | The first draft conference proceedings ready. | Done |
February 5, 2017 | The first draft conference program (with the photos version) ready. | Done |
March 1, 2017 |
Checkpoint 9: project reviews and progress monitoring. | Done |
March 1, 2017 | The official conference program ready (without photos). | Done |
March 15, 2017 | The first draft confirmed conference attendee list ready. | Done |
March 15, 2017 |
The official conference program ready (with photos). |
Done |
April 1, 2017 |
Checkpoint 10: project reviews and progress monitoring. | Done |
April 1, 2017 | The confirmed conference attendee list ready. | Done |
April 15, 2017 |
The official conference proceedings ready. |
Done |
April 27, 2017 |
Local Management Meeting. |
Done |
April 28, 2017 |
The EITA-B&M 2017 starts. |
Done |
April 28, 2017 |
The EITA-B&M 2017 ends. |
Done |
April 30, 2017 |
The final conference programs and proceedings ready. |
Done |