Project Milestones and Schedule
The EITA-Healthcare Venture 2018 project was started in April 2017 and runs through Spring 2018.
Date |
Project Milestone Description |
Status |
---|---|---|
April 1, 2017 |
Propose the conference and the location of the EITA-Healthcare Venture 2018. |
Done |
April 15, 2017 |
Propose the main theme of the EITA-Healthcare Venture 2018. |
Done |
April 29, 2017 | Set up the website of the EITA-Healthcare Venture 2018. |
Done |
April 29, 2017 | Decide the conference date. |
Done |
May 1, 2017 | Checkpoint 1: project reviews and progress monitoring. |
Done |
May 1, 2017 |
Start to draft the description of the conference theme. |
Done |
May 8, 2017 |
Start to propose the workshop schedule and the topics. |
Done |
May 15, 2017 |
Start to form the organizing committee and the program committee. |
Done |
May 20, 2017 |
Recommend the conference chair of the EITA-Healthcare Venture 2018. | Done |
May 26, 2017 |
Confirm the conference chair of the EITA-Healthcare Venture 2018. | Done |
May 27, 2017 |
Recommend the Project Manager of the EITA-Healthcare Venture 2018. | Done |
May 31, 2017 |
The website of the EITA-Healthcare Venture 2018 ready to support the event. | Done |
June 1, 2017 |
Checkpoint 2: project reviews and progress monitoring. | Done |
September 15, 2017 |
Confirm the Project Manager of the EITA-Healthcare Venture 2018. | Done |
June 30, 2017 |
Finalize the website of the EITA-Healthcare Venture 2018. | Done |
July 1, 2017 |
Checkpoint 4: project reviews and progress monitoring. |
Done |
July 1, 2017 | Start to draft the theme of precision medicine revolution. | Done |
July 15, 2017 | Propose the topics for all the panel sessions. | Done |
August 1, 2017 | Checkpoint 5: project reviews and progress monitoring. | Done |
August 28, 2017 | Start to form the organizing committee. | Done |
September 1, 2017 | Checkpoint 6: project reviews and progress monitoring. | Done |
October 7, 2017 | Start to invite program committee members. | Done |
November 1, 2017 |
Checkpoint 7: project reviews and progress monitoring. | Done |
November 15, 2017 | Finalize the conference themes and the program schedule. | Done |
December 1, 2017 |
Checkpoint 8: project reviews and progress monitoring. |
Done |
December 10, 2017 | The first draft template of the conference program ready. | Done |
December 10, 2017 | The first draft template of the conference proceedings ready. | Done |
December 29, 2017 | The official conference themes and the organizing committee ready. | Done |
January 1, 2018 |
Checkpoint 9: project reviews and progress monitoring. |
Done |
January 31, 2018 | The first local management meeting. | Done |
February 1, 2018 |
Checkpoint 10: project reviews and progress monitoring. |
Done |
March 1, 2018 |
Checkpoint 11: project reviews and progress monitoring. | Done |
March 15, 2018 | The draft of the conference program (without photos) ready. | Done |
March 17, 2018 | The draft of the letter of invitation ready. | Done |
March 18, 2018 | The template of the conference proceedings ready. | Done |
March 23, 2018 | The first draft confirmed conference attendee list ready. | Done |
April 1, 2018 |
Checkpoint 12: project reviews and progress monitoring. | Done |
April 15, 2018 | The confirmed conference attendee list ready. | Done |
April 15, 2018 |
The official conference proceedings ready. |
Done |
April 27, 2018 |
Local Management Meeting. |
Done |
April 27, 2018 |
The EITA-Healthcare Venture 2018 starts. | Done |
April 28, 2018 |
The EITA-Healthcare Venture 2018 ends. | Done |
May 4, 2018 |
The final conference programs and proceedings ready. |
Done |